by Louise Clare | Feb 13, 2024 | Uncategorized
Establishment Progress With construction now complete at 38 Agnes Street, Rockhampton, further finishing and commissioning tasks are well underway. This includes purchase and installation of additional equipment and furniture, landscaping, broader staff recruitment,...
by Louise Clare | Nov 24, 2023 | Uncategorized
Construction Progress The hospice build at 38 Agnes Street, Rockhampton is nearing completion! An enormous thank you to Tony Madden Architects, Paynters, and the many consultants and subcontractors who have worked tirelessly to bring the build in on time and on...
by Louise Clare | Sep 14, 2023 | Uncategorized
Construction Progress The hospice facility at 38 Agnes Street, Rockhampton is taking shape! All blockwork, structural steel and roofing is complete, and services rough-in and room fit-out is well underway. The build is on track for completion at the end of November,...
by Louise Clare | Jun 30, 2023 | Uncategorized
Construction Progress Building works for the hospice facility at 38 Agnes Street, Rockhampton continue to progress well. Despite some delays due to weather and subcontractor availability, the construction remains on track for completion in late 2023. All retaining...